Back to All Events

SBHS Entry Marquee (Lease Leaseback)


* Bids are due September 15, 2020 at 3:00PM

This Lease-Leaseback project consists of the following:  

The scope of this project is to construct a new digital marquee at the main campus entry of Santa Barbara High School.  The marquee will have a new concrete and stone base, a new custom fabricated aluminum display frame and support columns with ornamental mounting brackets and Hi-Resolution LED Display and new electrical work

Plans can be obtained on Smartbid or the following link:
https://schipperconstruction.box.com/s/6xdpnhl5nzuhna121cxtg1j2q4g8f1qu

If you have trouble accessing the files or would like a CD or electronic set, please contact us at info@schipperconstruction.com. We will have a hard copy set of plans in our plan room

This is a DSA Project

This project is  PREVAILING WAGE
MBW / WBE / DVBE Contractors are encouraged to bid

SB 693 & AB3018 is now in effect and all contractors working on this project must work to comply with these skilled workforce requirements.  Contractor agrees that skilled journeypersons employed to perform work on the Project by Contractor or its subcontractors at every tier are graduates of an apprenticeship program for the applicable occupation at the following percentages per Section 2601:  As of January 1, 2020, at least 60 percent of the skilled journeypersons employed to perform work on the contract or project by the entity and each of its subcontractors at every tier are graduates of an apprenticeship program for the applicable occupation that was either approved by the chief pursuant to Section 3075 of the Labor Code or located outside California and approved for federal purposes pursuant to the apprenticeship regulations adopted by the federal Secretary of Labor.

For the following trades, the requirement is 30%:

Acoustical Installer

Brick Layer

Carpenter

Cement Mason

Drywall installer / Lather

Marble Mason

Finisher or setter

Modular furniture or systems installer

Operating engineer

Pile Driver

Plasterer

FSCC Estimator:   Erwin Villegas erwin@schipperconstruction.com

SCOPE OF WORK:
The scope of work includes hard demolition, site demolition, surveying, foundation concrete, masonry / stonework, ornamental iron / custom signage, painting and electrical.